Wilsonville Headquarters

Oregon Dental Association's headquarters is located in Wilsonville, Oregon. Our 12,626 square foot facility features a large multi-purpose conference room with catering facilities and a 20-seat board room. Organizations with offices in our building include: Dental Foundation of Oregon, Donated Dental Services and Oregon Society of Oral & Maxillofacial Surgeons.

 

 Archives (Click photos to expand in a new window)
Home, Sweet Home: ODA took occupancy of the Wilsonville headquarters on June 12.Home, Sweet Home June 12, 2006 (Wilsonville) - Staff began occupying the Wilsonville headquarters on June 12.
The Board Room seats 20 comfortably around a large table with built-in power, voice and data access. Whiteboards, flipcharts and audiovisual equipment will be installed in the coming weeks.
Welcome: The lobby features natural slate tile, a built-in reception desk and a small rock garden and fountain, reminders of the Tualatin gardens.The lobby's built-in reception desk and counter greets visitors. Natural slate tiles and a small rock garden and fountain are reminders of the Tualatin Japanese garden.
Let's Talk: Small conference rooms for 2-6 people are found throughout the first floor.The small conference rooms found throughout the first floor provide private meeting space for groups of two to six.
Project Central: The Work Center offers more than five times the project space of the Tualatin building.The Work Center provides more than five times the project space of the Tualatin building...once we remove the moving boxes.
 
WITH ICING ON TOP: Landscapers, carpetlayers, presidents and executive directors worked over the Memorial Day holiday as the new ODA office building in Wilsonville nears completion.With Icing on Top May 29, 2006 (Wilsonville) - Landscapers, carpetlayers, presidents and executive directors worked over the Memorial Day holiday as the new ODA office building in Wilsonville nears completion. Furniture is scheduled for delivery and installation on June 8 and 9. The Board of Trustees will conduct a walking tour and inspection of the project on June 10.
SIT DOWN, RELAX: A library dedicated to all ODA members will serve as an office away from home for visitors.A library dedicated to all ODA members will serve as an office away from home for visitors. Equipped with a computer workstation, coffee service and comfortable chairs, the library is located immediately adjacent to the reception area.
LAYOUT: A spacious workroom will accommodate projects of all sizes.A spacious workroom will accommodate projects of all sizes, as well as a central filing system and storage units. Additional storage and the computer server room are located at the back of the work area.
NORTHERN EXPOSURE: A view of the north side of the building.A view of the north side of the building shows new landscaping, the service sidewalk to the kitchen area, the balcony off the classroom and the HVAC units.
 
LOT SHOT: Paving crews completed blacktopping the parking lot May 16.Lot Shot May 16, 2006 (Wilsonville) - Paving crews completed blacktopping the parking lot at the new ODA Wilsonville headquarters on Tuesday afternoon, May 16. Interior finish work is ongoing with the building scheduled for substantial completion by Memorial Day and occupancy in early to mid-June.

 

STORAGE SPACE: Casework continues throughout the interior.Casework continues throughout the interior. This cabinetry and service counter are part of the first floor board room

PATIO: Installation of nature slate flooring is complete.Installation of natural slate flooring is complete in the entry areas, as well as the second floor balcony accessible from the conference center.

 
TILING ON: A tile contractor removes excess grout from a second-story restroom floor.Tiling On May 9, 2006 (Wilsonville) -  A tile contractor removes excess grout from a second-story restroom floor at the new ODA headquarters in Wilsonville. Wall tiles and flooring are virtually complete in all bathrooms on both floors. Slate floors in the building entries and second-floor deck will be installed this week.

DROPPING IN: The suspended ceiling gridwork is in place throughout the new office building.The suspended ceiling gridwork is in place throughout the building. The first floor board room is shown here.

GOING UP: OTIS Elevator workers install the ODA's new lift.Workers from the OTIS Elevator Company are currently constructing the lift in the shaft. The inclusion of an elevator in the new office building makes the second-floor conference area and offices
fully accessible.
 

GLAZED OVER: Glaziers put the final touches on exterior windows.Glazed Over Apr. 26, 2006 (Wilsonville) - Glaziers put the final touches on all exterior windows at the new ODA headquarters in Wilsonville this week, as seen in this view of the second floor east dormer office. Final wallboard installation, texturing and painting is commencing on both floors.

 

REGULATORY: HVAC units line the north side of the building.HVAC units line the north side of the building.

Curbing and the driveway are visible in this view of the parking lot.Curbing is in; parking lot paving will take place at the end of next week.

 
FULL METAL JACKET: Roof installation at the new ODA headquarters in Wilsonville nears completion.Full Metal Jacket Apr. 19, 2006 (Wilsonville) - Roof installation at the new ODA headquarters in Wilsonville is nearly complete. Venting and roof caps will be installed by next week. The roof was fabricated on site, using machinery that allowed the installers to produce custom lengths of roofing material.

 


I SPY: Surveyors shoot final elevations for parking lot grading.Surveyors are shooting final elevations for parking lot grading and installation of curbs and sidewalks.

 

 

 

 


 



BUSY, BUSY: Many trades are currently finalizing exterior finish details.Many trades are currently involved in finalizing the exterior finishes of the ODA building. 

 

Office Space: Workers began sheetrocking office interiors this week.Room With A View Apr. 12, 2006 (Wilsonville) - Many of the interior office spaces have been sheetrocked this week. Workers will begin taping and mudding the joints later next week.
South Hallway: Insulation and sheetrock work commences.The south hallway shows the progress of the insulation and sheetrock installations.

Conference Center - The second floor conference center and meeting space.

 

The second floor conference center.
 
BUTTONING UP: Masonry work is complete on the north elevation.Buttoning Up Apr. 4, 2006 (Wilsonville) - Masonry work is complete on the north elevation of the new ODA headquarters in Wilsonville. The roofing phase of the project will begin next week.

CLOSE-UP: A variety of stonework and new window mullions adorn the southeast corner.

This detail view of the southeast corner of the building reveals both the variety of stonework as well as the window mullions. The glazing process begins this week.

 

 
BRICK HOUSE - First story exterior masonry is complete. Second story work begins this week.Brick House Mar. 25, 2006 (Wilsonville) - This view of the building's southeast corner shows that first floor exterior masonry is complete. Crews will begin the second story application this week. 

 

 

CLOSE-UP: The east facade of the building shows first story masonry work is complete.First floor exterior masonry work is complete, as shown in this view of the east facade.

 


INSIDE JOB: Interior work continues during the drying out process.Inside Job: This photo of the south office area shows metal stud walls and heating ducts. Interior work continues during the drying out process. Click to expand.
 

A PRETTY FACE: Masonry crews begin applying the brick facade.A Pretty Face - Mar. 22, 2006 (Wilsonville) - The masonry crew began applying the brick facade to the east and north sides of the new ODA building this week. The exterior brickwork will be completed in approximately 10 days. The next exterior phase of the construction will be the installation of the metal roof system. At the present time, heater humidifier units are operating around the clock in the interior to reduce the moisture content of the wood framing. Nearly five gallons of water are eliminated both morning and evening.

CLOSE-UP: Exterior masonry installation.Exterior masonry detail.

 

DRYING OUT: Roofing felt and plastic sheeting allow the building to begin the dehumidification process.Drying Out - Mar. 19, 2006 (Wilsonville) - With roofing felt in place and plastic covering the windows, the new ODA building is currently "drying out." Humidifier heating units have been installed to lower the moisture content in the exterior wood framing. Internal metal stud walls are also in place. The drying process is scheduled to take a minimum of three weeks. During this time, the exterior masonry will be applied and the metal roof installed.

 

TREE TOPPER: Crews placed a small tree atop the new headquarters building.Topping Out - Mar. 13, 2006 (Wilsonville) - Crews marked the completion of the wood framing of the Wilsonville headquarters by installing a small fir tree atop the roof. According to Dave Watson of , the tree signals to the other trades that their work may now begin. The 'topping-out' ceremony traces its roots back to Germany and the lower Scandinavian countries. The tree also signifies that the highest and last piece of structural framework has been placed.

 

SHEATHING: Crews began installing roof sheathing the week of March 6.Sheathing - Mar. 8, 2006 (Wilsonville) - Crews began installing roof sheathing the week of March 6 at the site of the new Wilsonville headquarters building. Installation will continue for the next several days, followed by placement of roof felt. Once that process is complete, the building will begin a 'drying out' process before interior work begins. This photo looks northwest from the intersection of SW Parkway Avenue and SW Sun Place.

 

Taking Shape - March 2, 2006Taking Shape - Mar. 2, 2006 (Wilsonville) - The building continues to take shape; the roof truss system is nearly complete. This view of ODA's new headquarters looks northeast from SW Sun Place.

 

RAISING THE ROOF: Crews begin placing roof trusses on the new Wilsonville
            headquarters.

Raising the roof - Feb. 25, 2006 (Wilsonville) - Crews begin placing second story roof trusses on the ODA's new headquarters buidling, under construction in Wilsonville. The project is on schedule, with completion slated for Memorial Day. The roof will be completed during the next three weeks and then the building will undergo a 'drying out' process, prior to interior work.

 

BIG CHECK: The ODS Companies President and CEO Robert G. Gootee
            presents a check for $500,000 to ODA President Weston W. Heringer, Jr., DMD, as board chair Michael L.
            McKeel observes.

The 'Big Check' - Dec. 9, 2005 (Wilsonville) - ODA President Weston W. Heringer, Jr., DMD gratefully accepted a $500,000 check donated by The ODS Companies during the Executive Committee's December 9, 2005 meeting. "Thank you very much for everything you do for the Oregon Dental Association," Heringer said. "We truly do appreciate it." President and CEO Robert G. Gootee and Board Chair Michael L. McKeel, DMD offered the funds on behalf of the ODS Board of Directors. Gootee explained that the money was earmarked to offset the increased costs of materials that had recently weighed down the ODA's Wilsonville building project. "We want this building to represent the dental professional with pride," said Gootee. "We didn't want the price of cement and steel to compromise your vision." According to Project Manager David Aaroe of Fortis Construction, the increases in cement and steel prices were caused in large part by overseas construction projects--specifically in China--acquiring 82 percent of those materials produced in the U.S. Meanwhile, Hurricanes Katrina and Rita and the additional fill material needed to stabilize the building site were also factors in the cost overruns.

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

 
Oregon Dental Association
Post Office Box 3710, Wilsonville, Oregon 97070-3710
Phone: (503) 218-2010;  ·  (800) 452-5628
Email: info@oregondental.org